After a series of successful and comprehensive tests, including on its twin KLT-40 reactor system, the floating nuclear power plant Akademik Lomonosov is ready to start commercial operations, Russia's Rosatom announced today.


Akademik Lomonosov is 144 metres in length, 30 metres wide and has a displacement of 21,000 tonnes.



Akademik Lomonosov at Murmansk (Image: Afrikantov OKBM)


 

첫 부유형 원자력발전소 운영허가를 기다리는 러시아


배수량 2만 1,000톤


   러시아 국영원자력회사인 Rosatom사는 2기의 KLT-40 원자로를 장착한 부유식 원자력발전소(floating nuclear power plant)인 Akademik Lomonosov호가 일련의 성공적이고 포괄적인 시험을 마친 후 상업운영을 시작할 준비가 되었다고 2019년 4월 24일 발표했다.


Akademik Lomonosov호는 길이 144m, 폭 30m에 배수량은 2만 1,000톤에 달한다.


이 부유형 원자력발전소에 장착된 2기의 원자로는 2019년 3월 31일 전출력인 100%까지 성공적으로 가동된 바 있다. Rosatom사는 이 시험들을 통해 해당 원자력발전소의 주설비 및 보조설비의 안전성은 물론 자동 공정제어 시스템의 작동 안정성을 확인했다고 밝혔다.




Rosatom사의 원전운영 분야 자회사인 Rosenergoatom사 측은 이 부유형 원전에 대한 승인 인증서를 규제 당국이 곧 발급할 것이라고 밝혔다. 이렇게 되면 올 7월에는 운영허가가 발급될 전망이다.


이와 함께 러시아 북부 Chukotka 지역의 Pevek에서는 해당 원자력 발전소용 육상 구조물 및 유압 구조물, 지역 전력망에 송전하고 열을 보내기 위한 인프라가 올해 말까지 완성될 예정이다. Rosatom사는 관련 엔지니어링 작업이 일정에 맞춰 진행되고 있다고 밝혔다.


이 부유형 원자력 발전소는 여름에 Pevek 항으로 견인될 예정이며, 이 곳에 있는 Bilibino 원자력 발전소와 Chaunskaya 복합화력 발전소를 대체하게 된다. 올 12월까지 전력망에 연결되어 정상 발전을 시작할 것으로 예상된다.

ndsl.kr


edited by kcontents


The plant's two reactors were successfully brought up to 100% capacity on 31 March. These tests confirmed the operational stability of the main and auxiliary equipment of the plant, as well as the automatic process control systems, Rosatom said.




Andrei Petrov, director general of Rosenergoatom, Rosatom operator subsidiary, said an acceptance certificate for the unit would now be issued by the regulatory authorities with a view to the granting of an operating licence in July.


The Verge

edited by kcontents


At the same time, onshore and hydraulic structures for the plant, as well as infrastructure ensuring the transmission of electricity to the local grid and heating for the city’s network, are scheduled to be completed by the end of this year in Pevek, which is the Chukotka region of northern Russia. Engineering work is running to schedule, Rosatom said.




The plant is scheduled to be towed to the Port of Pevek during the summer shipping season where it will replacing the outgoing capacities of the Bilibino nuclear power plant and the Chaunskaya combined heat and power plant. It is expected to be connected to the power grid in December.