100억불 규모 쿠웨이트, 알-주르 석유화학단지 프로젝트 입찰 동향 VIDEO: PROJECTS: Kuwait pumps crude to Al-Zour oil refiner
PROJECTS: Kuwait pumps crude to Al-Zour oil refinery
Project is 97% complete
A general view of one of three Atmospheric Residue Desulphurisation units (ARDS) at the Al Zour Refinery, that is under construction in Al Zour, Kuwait, February 13,2020. Image used for illustrative purpose.
Kuwait has started to pump crude to Al-Zour refinery ahead of commissioning of one of the world's largest oil refining units, a local newspaper reported on Wednesday.
About 97 percent of the project in South Kuwait has been completed despite challenges arising from the coronavirus outbreak, the Arabic language daily Alanba said, quoting official oil sources in the OPEC member.
The state-owned Kuwait Integrated Petroleum Industries Company (KIPIC) had planned to supply crude to the refinery in mid-2020 but could not bring in engineers and technicians from abroad due to coronavirus curbs, it said.
쿠웨이트, 알-주르 석유화학단지 프로젝트 추진 동향
Kuwait Integrated Petroleum Industries Company (Kipic)가 추진하는 100억불 규모의 알-주르(Al-Zour) 석유화학단지 프로젝트와 관련, EPC사들은 2021년 말 이전에는 입찰 초청이 있을 것으로 기대하고 있다고 MEED가 소식통을 인용해 보도했다.
2B1st Consulting
edited by kcontents
동 프로젝트는 2018.12월 실시한 PQ 결과를 아직 발표하지 않았으며, 당시 다음과 같은 총 6개 컨소시움이 PQ를 제출했다.
- SK건설 (대한민국) / Petrofac (UK)
- Sinopec (중국) / Technicas Reunidas (스페인)
- 삼성엔지니어링 (대한민국) / CTCI (대만) / Consolidated Contractors Company (레바논)
- Saipem (이탈리아) / 현대건설 (대한민국)
- Fluor (US) / 대우건설(대한민국)
- 현대엔지니어링 (대한민국) / Tecnimont (이탈리아)
한편, 동 프로젝트가 추진 우선순위에서 밀려있다는 평가도 있는 것으로 전해진다.
MEED는 금년 7월 Kipic가 타당성조사 재수행과 FEED 변경을 고려중이라고 보도한 바 있으며, Covid-19 판데믹이 시장에 미칠 장기적인 영향에 따른 프로젝트 수익성과 관련하여 재평가할 것으로 예상했다.
한편, 금년 6월 Wood Group은 동 프로젝트의 FEED를 마쳤으며, Kipic의 사업범위 변경으로 계획보다 지연된 것으로 알려졌다.
< 출처: MEED (2020.12.7.)>