Video: How a double-deck highway is built inside the Seattle tunnel — with enough concrete for 9 football stadiums
Video: How a double-deck highway is built inside the Seattle tunnel — with enough concrete for 9 football stadiums
Crews working for Seattle Tunnel Partners assemble rebar for a section of the future west wall of the northbound
roadway inside the SR 99 tunnel. (WSDOT via Flickr)
BY KURT SCHLOSSER on July 14, 2016
Crews working for Seattle Tunnel Partners assemble rebar for a section of the future west wall of the northbound roadway inside the SR 99 tunnel. (WSDOT via Flickr)
Seattleites caught up in the twists and turns and starts and stops of Bertha, the SR 99 tunneling machine, might lose sight of the fact that trailing behind her boring efforts is a massive roadway-building project. A new video from the Washington State Department of Transportation sheds light on how the new double-deck highway is pieced together.
David Sowers, WSDOT deputy administrator, leads the tutorial on how a tunnel and a roadway can be constructed at the same time. It’s worth noting that Bertha has only travelled about a third of the 9,270 feet that she has to mine. But behind the machine, wall foundations, walls and elevated road surfaces are being put in place.
It all has to be done in a way that allows machinery and materials — specifically the concrete rings that make up the tunnel wall — to continue to be able to reach Bertha. The machine, by the way, is currently stopped for routine maintenance — take a look at the work that goes into that.
Sowers explains how the roadway foundations, or corbels, are built in 54-foot sections. The video shows rebar and concrete work and notes that after the formwork is removed a few days after pouring, the concrete actually cures under wet plastic blankets for another 28 days. The same process follows for the outer walls which eventually support the top deck of the roadway.
View Full Text