Full steam ahead for new Tuas mega port


Full steam ahead for new Tuas mega port


The Tuas Terminal will be developed in four phases over 30 years, with Phase 1 scheduled to be completed by the early 2020s.ST GRAPHICS


Project proceeding as planned despite industry downturn


Karamjit KaurSenior Aviation Correspondent 

Works are in full swing at the future Tuas port, with reclamation ongoing for two out of four phases of the development and more than 3km of caisson already installed to form the wharf.


The caisson, which sits on a foundation on the seabed, is a 28m-high concrete watertight structure - about the height of a 10-storey Housing Board block. Using caissons to build the wharf structure is faster than traditional methods like piling.




In all, 8.6km of caisson will have to be constructed under Phase 1 of the Tuas port project, which aims to grow the Singapore port, amid competition from other regional and global ports.


The new Tuas port - which will be twice the size of Ang Mo Kio town - will be opened progressively from 2021. When fully completed by 2040, it will be able to handle up to 65 million twenty-foot equivalent units of cargo a year, more than double what the port handled last year.


Work on the port, which will eventually house current operations at Pasir Panjang, Tanjong Pagar, Keppel and Brani container terminals, is proceeding as planned despite the current industry downturn.