UAE 바라카 원전 1호기 커미셔닝 시험 성공적 완료...공정율 88% Tests carried out at UAE nuclear plant Barakah



Tests carried out at UAE nuclear plant Barakah


The UAE's Emirates Nuclear Energy Corporation (ENEC) said it has completed certain important tests at Unit 1 of the Barakah Nuclear Energy Plant.


The UAE's Barakah nuclear plant is 65% complete. [Representational image of Barakah, by WAM] 


아부다비의 바라카 원전 1호기의 커미셔닝단계의 중요 시험들이 성공적으로 

완료됐다고 UAE 원자력청이 밝혔다.


이 시험의 완료는 본격적인 인계를 위한 중요한 상징적 의미도 포함되어 있다.


현재 1호기는 88%의 공정율을 보이고 있으며

2호기는 72%

3호기는 50%

4호기는 31%가 완료되어 전체 공정율은 65%를 나타내고 있다.


황기철  콘페이퍼 에디터

ki chul, hwang conpaper editor 




by Neha Bhatia on Jul 4, 2016 

The completion of these tests is a landmark in the plant's commissioning works.


Unit 1 of Barakah is now 88% complete, while Unit 2 is 72% ready.

Unit 3 is 50% complete and Unit 4 is 31% complete. 


Overall construction of the four units stands at 65%.


Unit 1's Structural Integrity Test (SIT) and Integrated Leak Rate Test (ILRT) were performed over a period of several weeks, with the UAE's Federal Authority for Nuclear Regulation (FANR) overseeing the procedures.


Both these tests determine a structure's integrity and robustness in terms of force and leak tightness, and its ability to perform safely under normal and extraordinary circumstances.


SIT evaluates the strength of the Reactor Containment Building (RCB), the structure at the heart of the plant, which houses the reactor and major components.


ILRT assesses the leak tightness of the containment building under a variety of conditions.

 

The results of both tests show that the RCB can perform its primary function – to contain radiation and prevent any radioactive release into the environment – under normal operation conditions as well as emergencies and extraordinary events.


The tests also show that the RCB was constructed in accordance with the required safety standards. 


ENEC’s teams worked closely with Korea Electric Power Corporation (KEPCO) and FANR throughout the complex testing process.


The tests form part of the structure's commissioning phase, WAM reported.


Other recent commissioning milestones completed safely and successfully on Unit 1 include Reactor Systems Flushing, Turbine Lube Oil Flushing, and Cold Hydrostatic Testing (CHT), which verified that the reactor coolant system and other associated systems met FANR’s regulations.


Remarking on the tests, Mohamed Al Hammadi, CEO of ENEC, said: "We are proud to have maintained our track record of safety and quality with the completion of SIT and ILRT.


"The commissioning phase of a nuclear energy plant is a critical step towards the first fuel load.


"Before loading the fuel it is essential that the plant is tested under the highest standards of safety, security and quality," Al Hammadi added. 